What's happening now?
Conducting test pit borings for foundation structure plan
Site civil plan 95% complete; approaching permit submittal
Audio, video and lighting plan anticipated by the end of September
General contractor selection process narrowed to 3 candidates
Construction documentation phase underway
Prayers for the Project:
Discernment in finalizing the site plan
Favor from the township and county for permit approval
Wisdom in final general contractor selection
Continued generosity toward the project
Clarity for our Pastors and Staff in all decisions